Lesson 1.1preview: 5:03full lesson: 13 min

Where the DS3 goes: position, clearance and ventilation

The unit beneath the module, 3/4 in (2 cm) below and above the casing, and the heat that sends the bill later.

What stays from the lesson, to keep at hand before you mount the first unit. The page numbers in the sources are the PDF pages of each document.

What this lesson solves

  • Each microinverter mounts on the racking, directly beneath the module: one micro under every two modules, one module on each input. Mark each position first, relative to the module junction box and other obstructions.
  • Leave at least 3/4 in (about 2 cm) below and above the casing for airflow. The older documents print 1.5 cm for the same 3/4 in; 3/4 in is 1.9 cm, so the newer manual's 2 cm is the right conversion.
  • Micros and connectors, DC and AC, go beneath the modules, out of direct rain, UV and other adverse weather.
  • Cooling is natural convection, with no fans. With poor ventilation the micro may enter power derating; above 100 °C the troubleshooting guide records an AC protection mode, and production resumes once the temperature drops.
  • Plan the space behind the module with the datasheet depth, 1.7 in (42.5 mm) for the DS3 and DS3-H, the largest value of the documents, plus the clearance below and above.

The numbers in this lesson, with sources

WhatValueFact
Clearance below and above the casing3/4 in (about 2 cm)6.4
Operating ambient temperature-40 °F to +149 °F (-40 °C to +65 °C)4.6
Storage temperature, not operation-40 °F to +185 °F (-40 °C to +85 °C)4.7
Full power up to an ambient of65 °C (149 °F)4.12
Depth, DS3 and DS3-H1.7 in (42.5 mm)4.4
Body of the microup to 80 °C (176 °F)4.11

Each value comes from the course fact base, with the document page or the code section on record.

Chapters

  1. Intro0:00
  2. 1Where it goes1:20
  3. 2The clearance for airflow2:53
  4. 3Rain and UV4:23
  5. 4Temperature and power derating4:57
  6. 5Depth: the space behind the module7:00
  7. 6Harsh and coastal sites8:03
  8. 7The roof in the US8:54
  9. 8The hot casing9:59
  10. 9The common mistake10:32
  11. 10Quick check11:03
  12. 11Checklist and next lesson11:33

Preview transcript

669 words

This is the text of the open part of this lesson. The full transcript comes with the course, along with the job site materials.

Intro

0:00

A tight roof, a customer who wants the equipment hidden, and the installer measuring the gap. But the microinverter's clearance is written in the manual, and it isn't a suggestion. Hi, I'm Sol. This is lesson one point one, on mechanical installation. And I'm Helios. I brought the tricky roof and a unit that needs air. Today's topic is where the DS3 goes: position, clearance and ventilation. A bad position doesn't show on day one. The datasheet warns that the unit can cut its power. By the end of this lesson, you'll choose each unit's position with the manual in hand. And I want an answer for the roof that doesn't leave room for the clearance. There is one, and it starts with knowing the roof: shingle, metal, tile, and the heat. Where do we start? Position, clearance or heat? In this order: position, clearance, rain and sun, temperature, depth, harsh sites and the US roof. And we close with the hot casing, which burns the hand of anyone who forgets it.

Where it goes

1:20

Chapter one. The user manual for North America, revision two point three, page nine. Each microinverter mounts on the PV racking, directly beneath the PV module or modules. Beneath the module. Not under the eave, not on a wall, not loose on the roof. So the position is already written. It isn't up to whoever climbs the roof. And the same page says low voltage DC wires run from each module straight to the micro. The datasheet's front page draws it: one microinverter under every two modules, one module on each input. So you plan one micro for every pair of modules. Page eleven, step three: mark the location of each microinverter on the rack, relative to the module junction box or other obstructions. Then install one microinverter at each marked location, with the hardware your racking vendor recommends. Marking first is how you keep each micro clear of the module junction box and anything else in the way. Page twelve has a special case: modules flush-mounted on the rooftop. There, the DC connectors, the antenna and the LED indicator of the micro face outwards. Outwards, because somebody has to see the LED, and the antenna has to reach the ECU. The drawing marks that side with one word: thoroughfare.

The clearance for airflow

2:53

Chapter two. Same manual, page eleven, in the warning under step three. Leave a minimum of two centimeters, three-quarters of an inch, of space below and above the casing, to allow proper airflow. Above too? So between the casing and the module. That's right. Below, toward the roof, and above, toward the module, so the air can flow. Three-quarters of an inch sounds like nothing. It disappears fast when the rail sits low. You saw this in lesson zero point two. The older DS3-H manual, revision one point one, page eleven: same sentence, another metric number. It prints one point five centimeters, next to the same three-quarters of an inch. And the quick installation guide, revision four point zero, prints one point five centimeters too. So which one do I use? One point five or two? The inch value is the same in all of them: three-quarters of an inch. That's one point nine centimeters. So the newer manual's two centimeters is the right conversion. In this course: at least three-quarters of an inch, about two centimeters. Three documents, one inch value. The card puts them side by side. Below and above, both. In this course it's a rule, not a suggestion.

Rain and UV

4:23

Chapter three. Same page eleven, the first line of that same warning. Install the microinverters, including the DC and AC connectors, beneath the PV modules. That protects them from direct exposure to rain, UV, or other adverse weather. And the warning covers the connectors, or just the unit? It covers them, in parentheses: the DC connectors and the AC connectors. So the spot is under the module, with air flowing below and above. Chapter four. The DS3 Series datasheet, revision two point three, page two.