Closing commissioning: the map, the labels and the handover
The two serial labels, the installation map, the sync with the ECU, the status on the portal, the job labels by edition, the tests, the inspection and the PTO paperwork, and the handover.
What to keep from the lesson. Page numbers in the sources are the PDF pages of each document.
What this lesson solves
- Each micro comes with 2 removable serial number labels: one goes to its position on the installation map, the other on the module frame.
- Add each UID in ID Management, typed or scanned, and press Sync; 100 % in Inverter Connection Progress means the connection is finished.
- On the customer list, “Working normally.” is the status that closes commissioning; yellow, red and gray each point to a different fix.
- Job labels follow the NEC edition your AHJ enforces, plus the IFC labels where the fire code is adopted; photograph each one before the crew leaves.
- Two gates before normal operation: the AHJ's inspection and the utility's written PTO, with no date promised for either. The ECU goes online the day the system is energized.
The numbers in this lesson, with sources
| What | Value | Fact |
|---|---|---|
| Serial number labels per micro | 2, removable | 16.27 |
| Installation map | appendix, last page of the manual | 11.17 |
| Map grid | 7 columns by 10 rows | 11.17 |
Each value comes from the course fact base, with the document page or the code section on record.
Chapters
- Intro0:00
- 1The two serial labels1:24
- 2The installation map2:23
- 3Syncing with the ECU3:53
- 4The status on the portal4:52
- 5The job labels, by edition6:18
- 6The tests before the inspection7:58
- 7The inspection and the PTO paperwork9:53
- 8The ECU online on energizing day12:57
- 9The handover14:18
- 10The common mistake16:10
- 11Quick check16:55
- 12Checklist and next lesson17:23
Preview transcript
1018 wordsThis is the text of the open part of this lesson. The full transcript comes with the course, along with the job site materials.
Intro
0:00The system's on, the portal turns green, and then comes the question that stalls the handover. Which micro sits under which module? It all starts with two labels. Hi, I'm Sol. This is lesson four point five, the one that closes commissioning. And I'm Helios. I bring the end of the job, when everybody wants off the roof. Today it's labels and paper: the serial numbers, the installation map, the job labels, the inspection, and the handover. Sounds like paperwork. It's what every service call and every warranty claim leans on, for years. By the end of this lesson, you'll close the job with the map complete, the labels photographed, and the folder ready. And I want to know where each thing is written. In the DS3 Series manual, the EMA Manager manual, the NEC edition your AHJ enforces, and the utility's own rules. Where do we start? With the two labels and the map. Then the ECU, the status on the portal, and the job labels. Then the tests, the inspection and the PTO paperwork, the ECU online, and the handover.
The two serial labels
1:24Chapter one. DS3 Series user manual, revision two point three, page sixteen, step ten. You saw it in lesson zero point five: each microinverter comes with two removable serial number labels. The drawing on the page shows both labels, with the same number, and where they sit on the unit. The first one completes the installation map, affixed at the right location. With a DS3, one label stands for two modules: one on each input. The second one can go on the module frame. It confirms the micro's position later, without taking the module down. And that number is the UID the ECU asks for: twelve digits, starting with a four, a five, a seven, or an eight. So both labels come off as you mount each micro. Once the module goes on top, there's nothing left to read. Chapter two. The notice on the same page says where the map is: in the appendix, on the last page of the manual.
The installation map
2:23And here it is, page twenty-nine: the installation map template. On top, the job: the installer and the owner, the PV module type, and the microinverter type, each with its quantity. Module type and micro type, with quantities. The map already counts the material on the roof. Below, the grid: seven columns and ten rows. Each cell is a position. The grid is a drawing of the roof. And seven by ten won't fit every roof. Notice one says it plainly: the arrangement on the map is designed for standard installations. That's why the template has a sheet field, sheet blank of blank. A big roof takes more than one sheet. And a north arrow, so the drawing matches the roof. The U.S. map card, page one, is another sheet for the same job. On it, each sticker covers two module images. And the card talks about one removable label per micro. The manual governs: two labels, one for the map and one for the frame. Lesson zero point two showed it. And notice three ties the map to the ECU: when you configure it, the ECU APP scans the serial numbers on the map.
Syncing with the ECU
3:53Chapter three. EMA Manager app manual, page sixty-two: ID Management. With Add, you type the UID or scan it with the camera. Then Sync, to update the UIDs onto the ECU. Lesson four point two: without Sync, what I typed never left the phone. Removing one works the same way, page sixty-three: select it, Delete, and Sync again. And how do I know every one made it? Inverter Connection Progress, page sixty-five. One hundred percent means the connection is finished. And from lesson four point three: a micro with no link on the portal? Select it, Add, and Send. The link shows after twenty minutes. This step closes with a comparison: every label on the map has its UID in the ECU, and none is left over.
The status on the portal
4:52Chapter four. The EMA website manual for installers, page five: the customer list. Those are customers in the Netherlands and France on that screen. A demo account, as the manual says. The page shows where the data sit. Your list shows your own customers. Each system carries a status icon. The page lists six texts. One is storage in sleep mode. That's for battery systems, and a DS3 system has no battery. That leaves five. One: working normally. Two: some micro-inverters' communication interrupted since the beginning of the day. Three: some micro-inverters have not been properly registered. That one's mine: a UID typed wrong, or one that missed the Sync. Four: ECU disconnected from the internet. Five: the system has never reported production data. In the app, the same statuses come as the colors of lesson four point three. EMA Manager app manual, page eleven, gives the cause of each. Grey, for one: the ECU can be online while the micros were never synchronized in the ECU during commissioning. If the status isn't working normally, commissioning isn't finished.
The job labels, by edition
6:18Chapter five. With the portal in the green, one walk-down before the inspector shows up: the labels. Lesson three point three took them edition by edition. Here they are as a final check. Rapid shutdown first. Under the twenty seventeen NEC, six ninety point fifty-six C: on or within three feet of the service disconnect. Under the twenty twenty-three NEC, six ninety point twelve D: at each service equipment location, or an approved, readily visible spot. It shows where the initiation devices are, with a simple building and roof diagram. The twenty twenty-six edition keeps that rule. And where the AHJ adopted the fire code? The IFC labels too, twelve oh five point four: type one or type two, within three feet of the service disconnect. And under the IFC, the rapid shutdown switch gets its own label, within three feet of it. And the rest of the panel? The directory of power sources at the service. And the point of interconnection, marked with the rated AC output current and the nominal AC voltage.
Job site materials in every lesson, questions inside the video, spaced review, a final exam and a certificate of completion with a public verification code. 7 days to cancel, with a full refund.